Srinagar, Nov 24: This building is designed to move with the earthquakes.

In one of India’s most earthquake-vulnerable regions, Kashmir, a major engineering initiative is shaping country’s largest purpose-designed hospital structure.

The six-storey structure at Lal Ded Hospital Srinagar incorporates advanced seismic base-isolation technology, and is nearing completion soon.

The World Bank funded extension block at the premier maternity hospital has been conceived around earthquake-isolation technology from its design stage. Most such structures have the system introduced as a subsequent structural retrofit.

The building incorporates 43 friction pendulum isolators.

These are designed to reduce the transfer of seismic forces from the ground to the structure during an earthquake.

The LD Hospital project is the largest among three such base-isolation projects in India. The project is among the India’s significant applications of the technology in hospital infrastructure.

This project is being executed under the Jhelum and Tawi Flood Recovery Project (JTFRP).

Medical Superintendent Lal Ded Hospital, Dr Muzaffar Jan said the project is an engineering marvel, not just for J&K, but for the entire country.

The base-isolation system is the key and differentiating feature of the building’s structural design. In conventional construction the foundation is rigidly connected to the superstructure.

In base isolation system, specially engineered bearings allow controlled movement between the building and the ground during seismic activity.

The friction pendulum system uses sliding bearings with curved surfaces to help dissipate earthquake energy.

It also limits the forces transmitted to the structure.

The 43 isolators are intended to provide an additional layer of protection to a critical healthcare facility.

Dr Jan said the building can bear a quake upto the intensity of 8 Richter scale.

The design and engineering components have undergone technical vetting by premier institutions.

This project demonstrates a significant application of advanced seismic engineering in public healthcare infrastructure.

The MS, Dr Jan, said the original allotted cost of Rs 118.22 crore has been revised to Rs 127.75 crore now.

The G+5 structure with an attic has a total built-up area of 11,640 square metres. Its specialised bed strength has been revised from 108 to 117.  It will have 65 adult beds and 52 infant beds. The block will house specialties of gynae-oncology and assisted fertility and will house specialised healthcare infrastructure.

This includes modular operation theatres, intensive care units, high-dependency units, neonatal intensive care facilities, Labour, Delivery and Recovery suites, IVF laboratories and advanced foetal intervention facilities. Component-wise progress shows civil works at 75 percent.  On the same lines, electrical works have been completed 78 percent while mechanical works are at 71 percent.

Sixty-two percent medical equipment has been procured.

The agreement for execution of the project was signed on August 1, 2025.  The original completion deadline was December 31, 2026, and now the revised completion date has been fixed as February 28, 2027.

The project is part of the reconstruction and augmentation of critical hospital infrastructure under the World Bank-funded JTFRP.

The proposal was approved in 2017, but the project subsequently faced prolonged delays.